Standard Physical Progress

GMS-CDC2 implementation is at 71% compared with elapsed time at 31 March 2015 (48 months of 57 months or 84%). This lag is due to late approval of AOP every year. The standardized physical progress is 84.5%. The compares of weight progress of 71% with an elapsed period of 84% since project effectiveness (22 March 2011, or, 48 months). The approved procurement plan which included carried over main procurement items has been mostly completed in this reporting periods.

The main procurement items are Baseline household survey for Model Healthy Villages, HFMD and Dengue Sero-prevalence study conducted by IPC, and Purchasing of laboratory equipment; Billboard construction and Recruitment of malaria consultant are being in process.Download